Which of the following is a key disadvantage of the Spiral Model in software development?
- 1It is not suitable and can be too costly for smaller projects✓
- 2It does not incorporate risk analysis
- 3It lacks documentation and approval controls
- 4It prevents adding new functionalities in later stages
Correct answer
It is not suitable and can be too costly for smaller projects