Which of the following formulas is correct for computing the Labour Efficiency Variance?
- 1Standard Labour Cost - Actual Labour Cost
- 2Standard Rate × (Standard Time - Actual Time)✓
- 3Actual Time × (Standard Rate - Actual Rate)
- 4Standard Rate × Idle Time
Correct answer
Standard Rate × (Standard Time - Actual Time)
Download Single Question PDF