Physics · Construction Management
Which of the following describes a procurement/bidding process rather than an actual type of engineering execution contract?
- 1Open tender✓
- 2Item rate contract
- 3Lump-sum contract
- 4Build-Operate-Transfer (BOT) contract
Correct answer
Open tender