Physics · Hydroelectric Power Plants
Which of the following criteria is NOT primary when selecting a suitable site for a hydroelectric power plant?
- 1Sufficiently large catchment area
- 2Stable rocky foundation for dam construction
- 3Reliable water availability throughout the year
- 4High atmospheric altitude of the region✓
Correct answer
High atmospheric altitude of the region