General Studies · Project Management - Network Diagrams
Which of the following correctly distinguishes a 'dummy activity' in an Activity-on-Arc (AOA) network from a regular activity?
- 1A dummy activity is performed by junior staff and consumes minimal resources
- 2A dummy activity is an optional task that can be omitted without affecting the critical path
- 3A dummy activity represents any task with positive slack that lies off the critical path
- 4A dummy activity has zero duration and zero resource consumption, existing solely to correctly represent logical dependency relationships✓
Correct answer
A dummy activity has zero duration and zero resource consumption, existing solely to correctly represent logical dependency relationships
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management - Network Diagrams?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Project Management - Network Diagrams