Which of the following construction activities of a High Tension (HT) line is performed first to indicate the location of poles?
- 1Paying and stringing of conductors
- 2Guarding
- 3Sagging and tensioning of conductors
- 4Pit marking and digging✓
Correct answer
Pit marking and digging