Which of the following causes ranking conflicts between Net Present Value (NPV) and Internal Rate of Return (IRR)?
- 1All of the above✓
- 2Differences in project lifespans
- 3Differences in scale/size of the projects
- 4Differences in cash flow timing/patterns
Correct answer
All of the above