Which of the following best explains Take-or-Pay Contracts commonly used in infrastructure projects?
- 1Contract is valid only for export transactions
- 2Payment depends entirely on prevailing market price fluctuations
- 3Buyer must pay for a minimum specified quantity regardless of actual consumption✓
- 4Buyer pays only if goods or services are delivered
Correct answer
Buyer must pay for a minimum specified quantity regardless of actual consumption
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Finance?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Contracts?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Finance · Project Contracts