Which of the following best distinguishes PERT from CPM?
- 1PERT uses deterministic time estimates, while CPM uses probabilistic estimates
- 2PERT focuses exclusively on cost optimization
- 3CPM is used only for academic research projects
- 4PERT uses probabilistic time estimates, while CPM assumes deterministic activity times✓
Correct answer
PERT uses probabilistic time estimates, while CPM assumes deterministic activity times
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Business Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Business Studies · Project Management