Which of the following best defines 'contingency cost' in project budgeting?
- 1A fixed amount pre-allocated solely for official scope changes
- 2The core administrative expenditure of project management activities
- 3An additional surcharge directly billed to the client
- 4Funds reserved to cover unexpected expenses or identified risks during execution✓
Correct answer
Funds reserved to cover unexpected expenses or identified risks during execution
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management and Budgeting?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Project Management and Budgeting