Computer · Estimating and Costing
Which method of approximate estimation is generally preferred and most suitable for preparing an estimate of a factory building with multiple identical structural spans?
- 1Plinth area method
- 2Unit rate method
- 3Bay method✓
- 4Approximate quantity method
Correct answer
Bay method