General Studies · Industrial Engineering and Operational Research
Which management technique is most suitable for one-time projects involving activities of a non-repetitive nature where the time estimates are uncertain?
- 1PERT✓
- 2Simplex method
- 3CPM
- 4Resource smoothing
Correct answer
PERT