Which is the correct sequence for preparation of the surface for new pointing work?
- 1Cleaning surface and joints → Wetting surface and joints → Raking joints
- 2Raking joints → Cleaning surface and joints → Wetting surface and joints✓
- 3Cleaning surface and joints → Raking joints → Wetting surface and joints
- 4Wetting surface and joints → Raking joints → Cleaning surface and joints
Correct answer
Raking joints → Cleaning surface and joints → Wetting surface and joints
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Building Construction and Materials?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Building Construction and Materials