Computer · Estimation and Costing
Which document forms the primary official basis for standard rate analysis of civil works in India?
- 1The Contract Labour Act
- 2CPWD Schedule of Rates✓
- 3Standard Contractor Tender Form
- 4National Building Code
Correct answer
CPWD Schedule of Rates
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Estimation and Costing?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions