Which among the following estimates is prepared when a sanctioned estimate exceeds by more than 5%?
- 1Approximate Estimate
- 2Supplementary Estimate
- 3Revised Estimate✓
- 4Supplementary and Revised Estimate
Correct answer
Revised Estimate