Physics · Power Systems
Where is the draft tube, an airtight expanding pipe, physically located in a hydroelectric power station?
- 1At the entrance or beginning of the penstock
- 2In between the turbine runner exhaust and the tailrace✓
- 3In between the penstock and the turbine runner entrance
- 4Near the surge tank area
Correct answer
In between the turbine runner exhaust and the tailrace