When the sanctioned estimate is found to exceed or be significantly different from the actual requirement during execution, which of the following is prepared?
- 1An approximate estimate
- 2A revised estimate✓
- 3A repair estimate
- 4A supplementary estimate
Correct answer
A revised estimate