Computer · Estimation and Costing
When the sanctioned estimate exceeds by more than 5% due to rates being insufficient or structural changes, which type of fresh estimate is prepared?
- 1Revised estimate✓
- 2Special repairs estimate
- 3Supplementary estimate
- 4Cubic contents estimate
Correct answer
Revised estimate