When the sanctioned estimate exceeds by more than 5% due to insufficiency of rates or structural modifications, which type of estimate is prepared?
- 1Cubic contents estimate
- 2Supplementary estimate
- 3Special repairs estimate
- 4Revised estimate✓
Correct answer
Revised estimate