When the float or slack of an activity in a project network is positive, it indicates that:
- 1Extra time/resources are available and the project completion will not be delayed✓
- 2The project is behind schedule and additional resources are urgently required
- 3The activity is critical and any delay will delay the entire project
- 4The activity has been completed ahead of schedule
Correct answer
Extra time/resources are available and the project completion will not be delayed
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Construction Management