Computer · Construction Management
When the float or slack of an activity in a project network is positive, it indicates that:
- 1The activity has negative duration
- 2The activity is critical and any delay will delay the entire project
- 3The project is falling behind schedule and requires additional resources
- 4Extra time/resources are available and the project completion will not be delayed✓
Correct answer
Extra time/resources are available and the project completion will not be delayed
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Construction Management