Computer · Construction Management
When planning and scheduling different activities for a construction project, which quality/qualities is/are considered to calculate the total project duration?
- 1Both interdependency on other activities and the time taken by activity✓
- 2Only the time taken by activity
- 3Neither interdependency on other activities nor the time taken by activity
- 4Only interdependency on other activities
Correct answer
Both interdependency on other activities and the time taken by activity
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Construction Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Construction Management