Mathematics · Project Management and Network Analysis
When planning and scheduling activities for a construction project, which factor(s) must be considered to calculate the total project duration?
- 1Only interdependency among activities
- 2Neither interdependency among activities nor activity durations
- 3Only individual activity durations
- 4Both interdependency among activities and individual activity durations✓
Correct answer
Both interdependency among activities and individual activity durations
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management and Network Analysis?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Project Management and Network Analysis