When evaluating a new project using the NPV method, a firm's current Weighted Average Cost of Capital (WACC) should be adjusted for which of the following factors to be a theoretically correct discount rate?
- 1The depreciation charge related to the new project's non-current assets, as this impacts the cash flow available for distribution.
- 2The specific business risk and the specific financial risk of the new project, if different from the existing average company risks.✓
- 3The historical profitability of the new project's division, to account for management bias.
- 4The level of retained earnings available, as this represents the cheapest form of finance.
Correct answer
The specific business risk and the specific financial risk of the new project, if different from the existing average company risks.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Economics?
Practice full-length Economics mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Capital Budgeting?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Economics · Capital Budgeting