What is the process of planning the quantity and timing of production output over an intermediate time horizon, typically ranging from three months to a year, called?
- 1Master Production Scheduling
- 2Materials requirement planning
- 3Aggregate Planning✓
- 4Enterprise resource planning
Correct answer
Aggregate Planning