What is the primary purpose of using a Flow Process Chart in Method Study?
- 1To train workers on new technology
- 2To calculate the cost of production
- 3To record and analyse the sequence of activities in a process✓
- 4To design new machinery for production
Correct answer
To record and analyse the sequence of activities in a process