What is the primary purpose of the re-barring technique in building maintenance?
- 1To improve the thermal resistance of the building
- 2To increase the load-bearing capacity of an existing structure
- 3To provide surface finishing to exposed concrete
- 4To replace or add reinforcement bars in structural components✓
Correct answer
To replace or add reinforcement bars in structural components