General Studies · Industrial Engineering
What is the primary purpose of scheduling in Production Planning and Control (PPC)?
- 1To design new product layouts
- 2To determine the cost of raw materials
- 3To hire new operational personnel
- 4To prescribe the time for starting and completing each operation to ensure timely delivery✓
Correct answer
To prescribe the time for starting and completing each operation to ensure timely delivery