Computer · Irrigation Engineering
What is the primary purpose of constructing a diversion headwork across a river?
- 1To create a massive reservoir for long-term water storage
- 2To generate hydro-electricity on a commercial scale
- 3To raise the water level and divert river water into an off-take canal✓
- 4To scientifically measure the average regional rainfall
Correct answer
To raise the water level and divert river water into an off-take canal