What is the primary objective of using the PERT (Program Evaluation and Review Technique) approach in project management?
- 1To eliminate parallel activities within the project structure
- 2To optimize the allocation of non-human physical resources
- 3To focus primarily on strict time-cost trade-offs
- 4To focus on time estimation and scheduling of uncertain activities✓
Correct answer
To focus on time estimation and scheduling of uncertain activities
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Physics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Industrial Engineering?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Physics · Industrial Engineering