What is the primary objective of implementing a Monitoring and Evaluation (M&E) framework in development projects?
- 1To handle administrative and legal records of national railway networks
- 2To directly train technical computer engineers for private firms
- 3To civilly manage the physically engineering and building of highways
- 4To systematically track project progress, performance indicators, and long-term outcomes✓
Correct answer
To systematically track project progress, performance indicators, and long-term outcomes
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Social Science?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Project Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Social Science · Project Management