What is the correct sequence of steps required in an agrichemical-based power plant for electricity generation? (I) Feedstock Storage (II) Feedstock Preparation (III) Feedstock Identification (IV) Power generation
- 1I, II, IV and III
- 2I, III, II and IV
- 3III, I, II and IV✓
- 4IV, III, II and I
Correct answer
III, I, II and IV