What is the correct chronological order of engineering surveys conducted for a new highway alignment?
- 1Map Study, Reconnaissance, Preliminary Survey, Detailed Survey✓
- 2Preliminary Survey, Map Study, Reconnaissance, Detailed Survey
- 3Reconnaissance, Map Study, Detailed Survey, Preliminary Survey
- 4Reconnaissance, Detailed Survey, Preliminary Survey, Map Study
Correct answer
Map Study, Reconnaissance, Preliminary Survey, Detailed Survey
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Computer?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Highway Engineering?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Computer · Highway Engineering