What is the approximate quantity of cement (in kg) and dry sand (in cubic meters) required respectively for preparing 1 m3 of wet cement mortar in a 1 : 5 proportion?
- 1312 and 1.04✓
- 2290 and 1.00
- 3290 and 1.04
- 4270 and 1.00
Correct answer
312 and 1.04