What is a fundamental difference between PERT (Program Evaluation and Review Technique) and CPM (Critical Path Method)?
- 1Cost optimization is only possible in CPM and completely ignored in PERT.
- 2PERT is deterministic, while CPM is probabilistic.
- 3PERT is used exclusively in workshops, while CPM is used in plants.
- 4PERT is event-oriented, whereas CPM is activity-oriented.✓
Correct answer
PERT is event-oriented, whereas CPM is activity-oriented.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Physics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Industrial Management?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Physics · Industrial Management