Using an interest rate of 15% per year, the net present value (NPV) of a project has been correctly calculated as $850. If the interest rate is increased by 5%, the NPV of the project falls by $900. What is the approximate internal rate of return (IRR) of the project?
- 114.7%
- 217.4%
- 319.7%✓
- 420.3%
Correct answer
19.7%