Computer · Estimating, Costing and Valuation
Under which contract clause is a contractor reimbursed for variations in the value of the work executed due to fluctuations in the prices of materials and labour?
- 1Recovery of security deposit clause
- 2Price variation clause✓
- 3Compensation for delay clause
- 4Payment to third party clause
Correct answer
Price variation clause