Under the general principles of contracting and estimating, if any alterations are to be made in the tenders, it must be done only after obtaining prior sanction from the ________.
- 1purchase manager
- 2ordering authority
- 3engineer-in-charge
- 4competent authority✓
Correct answer
competent authority