Two workers A and B working together completed a job in 8 days. If A had worked with twice his actual efficiency and B had worked with 60% of his actual efficiency, the work would have been completed in 6 days. To complete the job alone, B would require how many days?
- 115 days
- 217 days
- 3845 days✓
- 4735 days
Correct answer
845 days