To ensure stability and prevent swinging during a lift, the crane hook should be positioned:
- 1To the left of the load
- 2Accurately above the load's center of gravity✓
- 3Below the center of gravity
- 4At an angle to the load
Correct answer
Accurately above the load's center of gravity