Three workers X, Y, and Z can complete a construction project in 4 days if they work together. Worker X can complete the project alone in 10 days, while Worker Y can complete it alone in 15 days. Determine how long it would take Worker Z to complete the project alone.
- 114 days
- 212 days✓
- 315 days
- 410 days
Correct answer
12 days