Mathematics · Time and Work
Three persons, A, B and C can complete a piece of work in 72 days, 96 days and 120 days, respectively. A and B started working at the same time and C joined after 3 days. If A leaves the work after 6 more days, then in how many days can B and C complete the remaining work?
- 142 days
- 251 days
- 339 days✓
- 430 days
Correct answer
39 days