Mathematics · Overall Equipment Effectiveness (OEE)
The TPM team at a high-speed cheque processing unit calculated the Overall Equipment Effectiveness (OEE) for their primary machine to be 72.0%. The machine's rates were: Availability = 90% and Quality = 80%. To achieve a target OEE of 85.0%, assuming Availability remains at 90% and Quality is maximized to 100%, what is the minimum required Performance Rate, and what type of loss does this address?
- 1Minimum Performance Rate is 75.0%; it addresses Defect Losses.
- 2Minimum Performance Rate is 85.0%; it addresses Breakdown Losses.
- 3Minimum Performance Rate is 90.0%; it addresses Setup and Adjustment Losses.
- 4Minimum Performance Rate is 94.4%; it addresses Reduced Speed Losses.✓
Correct answer
Minimum Performance Rate is 94.4%; it addresses Reduced Speed Losses.
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for Mathematics?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Overall Equipment Effectiveness (OEE)?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in Mathematics · Overall Equipment Effectiveness (OEE)