Computer · Soil Mechanics
The total primary consolidation settlement (Sc) of a building constructed on a 10 m thick saturated clay layer is estimated to be 50 mm. After 300 days of the construction of the building, the primary consolidation settlement was reported as 10 mm. The additional time (in days) required to achieve 50% of Sc will be:
- 12150 days
- 21875 days
- 31575 days✓
- 41200 days
Correct answer
1575 days