The time taken by 'A' to complete a work is 12 days less than that taken by 'B' to complete the same work. Working together, they can complete the work in 8 days. Find the time taken by 'A' alone to complete the work.
- 118 days
- 216 days
- 312 days✓
- 410 days
Correct answer
12 days