The three-time estimates of a PERT activity, i.e., optimistic time, pessimistic time, and most likely time, are 7 min, 13 min, and 9 min, respectively. The expected time (in minutes) and the variance of the activity will be:
- 19.33 and 1✓
- 215.67 and 1
- 311.33 and 1.5
- 415.67 and 1.5
Correct answer
9.33 and 1