The table shows the activities, their durations, and dependencies in a project. What is the total duration of the project in days? ActivityDuration (days)Depends onA8-B4AC4BD4C, LF4AG4FH6G, LK10AL6F, K
- 132 days
- 224 days
- 328 days
- 430 days✓
Correct answer
30 days