The primary objective of using the total quantity method (or approximate quantity method) of estimation is for determining the:
- 1Total approximate cost of the project✓
- 2Profit margin of the contractor
- 3Specific types of materials required
- 4Exact quantities of individual work items
Correct answer
Total approximate cost of the project
Download Single Question PDF