The primary objective of the 'crashing' technique in the Critical Path Method (CPM) is to:
- 1Optimize the path by removing redundant resources
- 2Reduce the overall project duration at minimum additional cost✓
- 3Increase the duration of non-critical activities
- 4Decrease total project cost by altering specifications
Correct answer
Reduce the overall project duration at minimum additional cost
Download Single Question PDF
Save this question and verified answer as a clean study sheet with live clickable link.
Share with Friends & Study Groups
Challenge your peer aspirants on WhatsApp or Telegram to solve this question!
Preparing for General Studies?
Practice full-length mock tests with real exam timers, instant score analysis, and all-India ranking.
Want more practice questions on Industrial Engineering and Operations Research?
Solve complete topic-wise tests with detailed solutions on GkGet.
Related Practice Questions
Recommended practice questions in General Studies · Industrial Engineering and Operations Research