The optimistic time, most likely time, and pessimistic time of a PERT network activity are 6 days, 9 days, and 12 days respectively. The standard deviation and variance of the activity are, respectively:
- 11 and 2
- 21 and 1✓
- 32 and 1
- 42 and 2
Correct answer
1 and 1